THAMES TUNNEL
GRAVESEND TO TILBURY
In 1798 a tunnel was proposed by engineer Ralph Dodd, linking Gravesend to Tilbury Fort under the river Thames. This was intended to move troops from Gravesend barracks across the river more quickly to their destination. The tunnel was thought to have started 800 yards to the east of Tilbury Fort.
It was proposed to be a construction with key stones for extra strength. The diameter was planned to be 16 foot, to allow for foot, horse, and carriage transportation.
It also was planned to be illuminated with lamps, and had its own steam engine driving a pump, to remove drainage water. It had problems from the beginning and had continual flooding; eventually the whole project was abandoned, and was a disaster, at a cost of £15,000.
Comments about this page
Add your own comment
The second image depicts Brunel’s Thames Tunnel at Rotherhithe and not Dodd’s. The one at Tilbury was planned as a single tunnel.
Add a comment about this page